x
Send Your Inquiry Today
Quick Quote

LED Street Light RFQ and Specification Checklist

A useful LED street light RFQ checklist defines the project, roadway and pole geometry, lighting targets, luminaire configuration, electrical and control requirements, required evidence, quantity, delivery destination, and acceptance process. Use the same schedule for every bidder so price and performance are compared against equal scope.

This guide is for procurement teams, contractors, consultants, distributors, and project owners preparing a road-lighting request for quotation. It helps turn a broad lighting need into a controlled bid package, then carries the same requirements through technical review, sample approval, production, and receiving inspection.

The key inputs are the project scope, roadway geometry, maintained lighting criteria, luminaire schedule, submittal register, sample and acceptance gates, and deviation process. The final verification step is to confirm that the awarded configuration, documents, sample, and delivered quantity still match the approved RFQ—not merely the supplier’s first quotation.

Define the Project and Bid Scope

Start by defining what the supplier must price, design, document, and deliver. A street-light quotation is difficult to compare when one bidder includes photometric design and controls while another prices only the luminaire. The RFQ should identify the country or market, application, project stage, quantity, delivery destination, required date, and every included or excluded service.

State whether the bid includes poles, arms, foundations, luminaires, photocells or other controls, wiring, installation, commissioning, photometric simulation, samples, spare units, packing, and on-site support. If the buyer has already designed the pole layout, require the bidder to price against that layout. If the bidder must complete the lighting design, provide the input drawings and define the required output.

Ask bidders to identify assumptions and questions before the quotation deadline. Issue one controlled clarification log and record the revision number on every drawing, schedule, and addendum. This prevents a late email or superseded drawing from becoming an untraceable commercial difference.

Scope-Responsibility Table

Scope itemBuyer provides or confirmsBidder provides or confirmsInclude in base bid?
Project and deliveryCountry, site, destination, quantity, scheduleLead-time assumption and delivery basisYes / state exception
Roadway designDrawings, road class or target criteria, pole layoutPhotometric review or design responseDefine clearly
LuminairesRequired performance fields and approved alternativesExact catalog code and option mappingYes
Poles and mountingExisting or new pole data, arm interfaceMounting compatibility and accessoriesSeparate line if excluded
ControlsRequired photocell, dimming, sensor, or network interfaceWiring diagram and control compatibilityDefine by model/configuration
DocumentsRequired bid and approval documentsDatasheet, drawing, photometric file, compliance evidenceYes
Samples and acceptanceSample quantity, approver, inspection methodSample, test data, corrective actionDefine gate
Installation and commissioningSite responsibility and access conditionsInstallation guidance or field service scopeOptional or separate

 

The table should be part of the RFQ, not an informal internal note. Mark each line as included, excluded, optional, or to be confirmed. That classification gives bidders less room to interpret the commercial scope differently.

Attach Roadway Pole and Lighting Inputs

A supplier needs roadway geometry before a luminaire can be meaningfully selected. Attach a plan view, road cross-section, pole schedule, and photographs or survey information where existing conditions may affect the result. Identify road width, lane count, sidewalks, shoulders, medians, intersections, curves, driveways, and conflict points.

For each pole position, provide mounting height, outreach length, tilt or arm angle, setback from the pavement, spacing, orientation, and existing mounting interface. Note whether the arrangement is single-sided, staggered, opposite, median-mounted, or another layout. Record obstructions such as trees, signs, utility lines, barriers, buildings, and parapets that could change the useful light distribution.

State the target maintained criteria and the documents that govern them. The RFQ should distinguish the project’s required lighting result from a supplier’s nominal lumen claim. Depending on the project, the criteria may include maintained illuminance, uniformity, glare or intensity limits, lighting class, calculation grid, maintenance assumptions, and approval method. These requirements must be tied to the applicable project documents and target market rather than presented as universal values.

Mandatory-Input Checklist

  • ☐ Country, project location, application, project stage, and delivery destination
  • ☐ Roadway plan, cross-section, lane dimensions, sidewalk or shoulder information
  • ☐ Pole positions, mounting height, outreach, tilt, setback, and spacing
  • ☐ Existing pole, arm, tenon, junction-box, and cable-interface constraints
  • ☐ Layout type: single-sided, staggered, opposite, median, intersection, or other
  • ☐ Target maintained criteria, calculation grid, maintenance factor, and approval basis
  • ☐ Applicable client, municipal, utility, or project documents
  • ☐ Available voltage, frequency, grounding, surge protection, and circuit information
  • ☐ Control method, photocell or sensor requirements, dimming schedule, and interface
  • ☐ Environmental conditions, corrosion exposure, wind or vibration concerns, and access limits
  • ☐ Required drawing, IES/LDT, wiring, compliance, warranty, and inspection documents
  • ☐ Quantity by location or luminaire type, required spares, packing, and delivery schedule

Do not ask a bidder to “recommend a suitable street light” without supplying these inputs or explicitly paying for a design stage. A wattage recommendation without geometry and maintained criteria cannot prove road coverage, uniformity, glare performance, or mounting compatibility. For more detail on output, illuminance, uniformity, and optics, link this section to the LED street light lumens and lux guide. When pole height and spacing drive the result, direct readers to the street light pole height and spacing guide.

Create the Luminaire Schedule

The luminaire schedule converts the project brief into fields that every bidder must answer. Specify performance requirements without preselecting an unverifiable marketing claim. Use the required lighting result, electrical limits, optical distribution, mounting, controls, environmental protection, finish, labels, and accessories as the comparison framework.

Output should be stated using the project’s required measurement basis. Ask for rated or tested luminous flux, power, efficacy, correlated color temperature, color rendering information, and operating conditions where those fields matter. Identify whether the value is required, preferred, or subject to the supplier’s proposed configuration. Do not accept a range without the exact product code, option code, and configuration that produces it.

Specify the optic or distribution in the language used by the project. A Type III, Type IV, or Type V designation alone does not replace a photometric file and layout review. Require the supplier to state mounting orientation, tilt assumptions, lens or optic code, driver setting, and any factory-programmed dimming profile used in the submission.

Electrical fields should include input voltage and frequency, power factor or harmonic requirements if specified by the project, surge protection, grounding, dimming interface, photocell receptacle, sensor, connector, and cable entry. Environmental fields may include ingress protection, impact resistance, finish, corrosion requirements, operating temperature, and cleaning or maintenance conditions. Each field must be linked to the exact offered model and market documentation.

Luminaire Schedule Template

FieldBuyer requirement or questionBidder response
Luminaire type and applicationRoadway location, layout, and quantity 
Exact catalog codeComplete base model and option mapping 
Rated luminous outputValue, unit, test/configuration basis 
Input powerMaximum or target, with driver setting 
Optic/distributionRequired distribution and optic code 
MountingTenon, slip fitter, arm, bracket, tilt, hardware 
Input voltage/frequencyAvailable supply and acceptable range 
ControlsPhotocell, dimming, sensor, protocol, wiring 
Protection and finishRequired IP/IK, corrosion, color, labels 
Photometric dataMatching IES/LDT file and calculation assumptions 
AccessoriesReceptacle, shield, cable, adapter, spare parts 
Warranty and deviationsTerm, conditions, exclusions, deviation reference 

 

Require exact catalog codes and option mapping. “Equivalent” is not a sufficient response if the bidder has not identified the optic, driver, control, mounting, finish, and certification or compliance configuration. If the project permits alternatives, create a separate alternative line so the base bid remains comparable.

For a complete product-selection workflow, link this stage to the LED street light buying guide. If the application is actually a parking area, yard, campus, or commercial property rather than a road, use the area-light definition and coverage guide instead of forcing roadway assumptions into the schedule.

Define Evidence and Submittals

A quotation is not complete evidence of compliance. The RFQ should request documents that allow the buyer to trace each important claim to the offered configuration. Separate bid-stage documents from approval-stage deliverables so bidders know what is required before price comparison and what is required before production.

At bid stage, request a completed compliance schedule, product datasheet, dimensional drawing, exact model and option codes, photometric file, wiring information, control description, deviations, warranty terms, and a list of required test or compliance documents. If a photometric design is part of the bid, require the calculation file or report and state the assumed pole geometry, optic, tilt, maintenance factor, and mounting arrangement.

At approval stage, require the final controlled drawing, production configuration, approved sample record, matching photometric file, wiring and installation instructions, labels, packing information, inspection records, and the documents required by the project or target market. Certification and compliance statements must be tied to the actual model, power, configuration, and market. IP or IK ratings should not be treated as a substitute for a separate third-party certification.

Submittal Register

DocumentBid stageApproval stageAcceptance check
Completed technical compliance scheduleRequiredUpdated if changedAll fields answered
Datasheet and exact model codeRequiredControlled revisionCode matches quotation and sample
Dimension and mounting drawingRequiredApproved revisionInterface and tilt verified
Matching IES/LDT photometric fileIf design is includedRequired for final configurationFile matches optic, power, and driver setting
Wiring and control diagramRequired where controls applyApproved final versionInterface and terminals verified
Test/compliance documentsAs required by projectRequired before approvalScope, model, market, and validity checked
Warranty termsRequiredFinal commercial recordConditions and exclusions recorded
Deviation scheduleRequiredClosed before award/productionEach item has written disposition
Inspection and packing recordsUsually approval/productionRequired before shipment if specifiedQuantity and identification traceable

 

Request a deviation schedule even when the bidder believes the offer is fully compliant. A blank deviation field can hide assumptions; a signed “no deviations” statement is clearer. The buyer should not infer compliance from silence, a generic brochure, or a higher-looking performance number from another configuration.

Plan Samples Production and Acceptance

Samples should be placed at a defined procurement gate, not ordered automatically with the first quotation. For a low-risk replacement with a fully documented, previously approved configuration, a document review may be sufficient. For a new roadway, unfamiliar supplier, nonstandard mounting interface, important control system, or high-consequence project, a sample or pilot installation can reduce approval and production risk.

Define sample quantity, sample configuration, inspection criteria, responsible approver, and the records required. Check dimensions, mounting fit, finish, labels, connector and wiring arrangement, control response, driver setting, optical file match, and visible workmanship. If a photometric or installation check is required, identify the test method, measurement points, acceptance tolerance, and who owns the final decision.

Preproduction approval should freeze the approved model, optic, power, control, mounting, finish, label, packaging, and revision. Any proposed change after approval should trigger written change control and a decision on whether a new sample or updated documents are required. Define packing, spare quantity, identification, receiving inspection, damage reporting, and nonconforming-product handling before shipment.

Procurement-Gate Timeline

  1. RFQ issue:Release the controlled scope, drawings, schedules, document list, commercial basis, and response deadline.
  2. Bidder questions:Collect questions in one log, issue answers or addenda to all bidders, and record the revision.
  3. Technical review:Check the completed schedule, exact configuration, geometry assumptions, documents, deviations, and commercial exclusions.
  4. Shortlist and sample decision:Decide whether the risk profile requires a sample, pilot, photometric review, or installation check.
  5. Sample approval:Record inspection results, open actions, approver, and approved configuration revision.
  6. Preproduction release:Close deviations and change-control items before authorizing production.
  7. Production and shipment:Require agreed identification, packing, spares, inspection records, and controlled documents.
  8. Receiving and final acceptance:Verify quantity, model, accessories, damage, labels, documents, and any site or photometric checks.

State who approves each gate: buyer, lighting consultant, electrical engineer, owner, utility, or another designated authority. “Approved by the project team” is too vague for a dispute or later change.

For mechanical, electrical, and control coordination, link to the street light installation and wiring guide. The installation section should not be silently replaced by assumptions made during procurement.

Compare Responses and Close Deviations

Use a common comparison method after every bidder has responded against the same RFQ revision. Separate technical compliance, commercial scope, delivery, documentation, and options. Normalize exclusions, optional items, trade terms, taxes or freight basis, delivery destination, payment conditions, sample cost, spare units, and installation or design services before comparing totals.

A lower price may reflect missing photometric work, omitted controls, a different optic, no sample, shorter warranty conditions, excluded freight, or an unclosed deviation. The comparison matrix should make those differences visible rather than hiding them inside a single total.

Bidder Comparison Matrix

Comparison fieldBidder ABidder BBidder C
Exact luminaire code and option mapping   
Proposed output, power, optic, and mounting   
Voltage, control, protection, and accessories   
Photometric file and design assumptions   
Required documents received   
Deviations and exclusions   
Sample or pilot proposal   
Unit price and included scope   
Freight, trade terms, taxes, and destination basis   
Delivery proposal and schedule assumptions   
Warranty terms and conditions   
Spares, packing, and receiving support   
Technical/commercial status   

 

Require written resolution of every deviation before award. The resolution should identify the original requirement, the bidder’s proposed exception, the agreed correction or acceptance, the responsible person, and the controlled revision. Do not close a deviation through a phone call alone.

FY LIGHTING integration: Send FY LIGHTING the completed RFQ schedule with road drawings, pole data, target lighting criteria, required SLE power and optic options if known, voltage, controls, quantity, destination, documentation list, and timeline. FY LIGHTING can respond against the same fields and identify configuration questions before quotation approval. Any final model, performance, documentation, certification, warranty, and delivery statement should be confirmed for the exact proposed configuration and market.

Frequently Asked Questions

What Information Is Essential in a Street-Light RFQ?

At minimum, include roadway and pole geometry, target maintained criteria, luminaire performance and mounting requirements, voltage and controls, required evidence, quantity, delivery scope, and acceptance gates. Adding drawings, exact response fields, and a deviation schedule makes bids easier to compare and reduces assumptions.

Should the Buyer Specify Wattage?

Wattage can be a useful limit or budget-control field, but it should not replace the required lighting result and photometric review. Start with geometry, maintained criteria, optic, mounting height, and controls. Then ask bidders to state the exact power and configuration that meets those conditions. A wattage-only specification can reward an unsuitable distribution.

How Should Supplier Deviations Be Handled?

Require a visible deviation schedule and written closure. Each deviation should state the original requirement, the proposed exception, its technical or commercial effect, the agreed disposition, and the responsible approver. Close deviations before award or production; do not treat silence or a generic “compliant” statement as approval.

When Should a Sample Be Ordered?

Order a sample after the technical shortlist and before production approval when the project has meaningful interface, optical, control, quality, or supplier risk. A sample is especially useful for new pole interfaces, unfamiliar controls, nonstandard options, pilot roads, or projects where replacement would be costly. Define the inspection method and approver before ordering it.

What Should a Buyer Request With the Quotation?

Request the completed compliance schedule, exact catalog and option codes, datasheet, dimension drawing, matching photometric file when applicable, wiring and control information, required compliance documents, warranty terms, delivery basis, exclusions, and deviation schedule. This package lets the buyer compare the offered configuration rather than a general product family.

What Is the Next Step After Comparing Bids?

Select the technically acceptable configuration first, close every deviation in writing, decide whether a sample or photometric check is needed, and freeze the approved revision before production. Then verify delivered quantity, model, accessories, labels, documents, and any agreed site acceptance checks against that revision.

Conclusion and Call to Action

A strong LED street light RFQ checklist makes the bid comparable before price enters the discussion. Define the project scope, attach roadway and pole inputs, create a complete luminaire schedule, request traceable submittals, establish sample and acceptance gates, and close deviations in writing.

Send the completed project inputs to FY LIGHTING for a configuration review based on the exact application: road drawings, pole data, target lighting criteria, voltage, controls, quantity, destination, documentation requirements, and timeline. The practical goal is not simply to receive more quotations; it is to receive responses that can be checked, approved, produced, and accepted against the same requirements.

FY Lighting — Professional LED Solutions for Every Industry

FY Lighting specializes in high-performance LED systems for industrial, explosion-proof, and agricultural applications. From factory lighting to vertical farming solutions, we help clients worldwide achieve safety, efficiency, and sustainability.
en_USEnglish
Scroll to Top