Installing LED high bay lights is not simply a matter of hanging a fixture and connecting power. A safe installation requires approved product documents, a verified mounting structure, suitable access equipment, qualified electrical work, correct positioning, and commissioning records. The exact hardware, wiring method, torque, enclosure requirements, and control settings must come from the selected model’s installation documentation and the applicable local requirements.
This guide explains the installation-management sequence for commercial and industrial projects. It does not replace the luminaire installation manual, structural engineering, lockout/tagout procedures, electrical inspection, fall-protection planning, or the responsibility of qualified installers.
Quick Answer: What Is the Correct Installation Sequence?
To install and hang LED high bay lights, first approve the layout and product documents, isolate the work area, verify the structure and mounting points, select a model-supported mounting method, position each fixture from the lighting layout, protect cable entries and enclosures, configure sensors or emergency options, and complete mechanical, electrical, control, and light-level checks. Do not choose a universal height or fastening detail without the model, structure, environment, and local requirements.
Conditions That Change the Installation Answer
The correct method depends on several project inputs:
- The fixture series, exact wattage, dimensions, weight, mounting accessories, and installation manual.
- Mounting height, ceiling or support construction, vibration, seismic conditions, and access limitations.
- Supply voltage, control method, emergency configuration, sensor type, and cable-entry arrangement.
- Ambient temperature, humidity, dust, washdown exposure, corrosive agents, and indoor or outdoor location.
- Required illumination, uniformity, aisle orientation, work-plane height, and the approved photometric layout.
- Local structural, electrical, fire, workplace-safety, and inspection requirements.
A fixture that is suitable for one high-bay project may not be suitable for another if its mounting interface, enclosure, temperature range, control option, or certification coverage differs.
The Decision Path
Use this sequence: documents and safety boundary → structure and mounting points → mounting method → coordinates and orientation → cable and enclosure protection → controls and emergency components → commissioning and handover. If a step cannot be verified, stop and resolve the missing information before proceeding to the next stage.
Installation Safety Module
Before the first fixture is lifted, the responsible team should confirm four controls: **work authorization, access and fall protection, energy isolation, and overhead-object control**. The installation area should be barricaded or otherwise managed so people cannot pass beneath suspended work. Access equipment must be suitable for the height and task, and the work plan should address dropped objects, lifting, weather or washdown conditions, and rescue arrangements where applicable.
The qualified electrical team should establish and verify the isolation boundary before any electrical work. The structural or project authority should approve the support and mounting point. Only after these controls are in place should the installer move to the model-specific attachment sequence. The result to record is not merely “safe”: it is the approved work package, the isolation verification, the access method, the accepted support, and the person responsible for each check.
1. Review the Preinstallation Documents
Start With Qualified Roles and an Approved Work Package
Before equipment reaches the ceiling, define who is responsible for design approval, structural review, electrical isolation, installation, controls, inspection, and final acceptance. The same person may not perform every role. On a large facility, the project manager should maintain one controlled package containing the latest drawings, fixture schedule, product submittal, mounting details, control narrative, risk assessment, and inspection plan.
The work package should identify the exact luminaire model rather than only saying “LED high bay.” It should also state the quantity, location or grid reference, mounting accessory, input voltage, control option, emergency option, and any special environmental requirement. A generic product photograph is not enough to approve installation.
Check the Luminaire and Layout Documents
At minimum, compare the following documents before installation:
| Preinstallation item | What to verify | Why it matters |
| Luminaire schedule | Series, wattage, quantity, dimensions, weight, location and accessory code | Prevents the wrong fixture or accessory from reaching the work area |
| Approved layout | Fixture coordinates, mounting height, orientation, optic, work plane and predicted light levels | Establishes the intended optical result |
| Product documentation | Mounting method, cable entry, enclosure, driver, controls, emergency option and environmental limits | Prevents generic assumptions from replacing model instructions |
| Structural information | Support member, allowable load, fastener system, vibration and seismic requirements | Confirms the support can carry the installation and service loads |
| Electrical documents | Supply, circuiting, isolation point, protection and control architecture | Defines the qualified electrical work and inspection scope |
| Commissioning plan | Functional tests, sensor settings, emergency test, measurements and records | Makes acceptance repeatable rather than subjective |
The approved lighting layout should be treated as a set of coordinates and conditions, not as a suggestion to “hang the fixtures evenly.” A change in mounting height, optic, row alignment, ceiling reflectance, or work-plane elevation can change both average light and uniformity.
Verify Components Before Lifting Fixtures
Inspect the fixture, mounting hardware, safety cable or secondary retention, junction boxes, glands, seals, connectors, control devices, emergency parts, and labels. Confirm that each component is approved for the model and environment. Do not substitute a hook, chain, cable, bracket, gland, or junction box because it looks similar.
Also check for shipping damage, loose lenses, damaged cable jackets, missing plugs, distorted seals, and moisture inside the enclosure. Record discrepancies with photographs and hold the affected item for review. A damaged enclosure may compromise the system even if the light turns on during a temporary test.
2. Verify the Structure and Mounting Points
Identify the Actual Load Path
The fixture does not hang from “the ceiling” in a general sense. Its load travels through the approved mounting accessory, fastener, support member, and building structure. The design team or qualified structural reviewer should confirm the load path, allowable capacity, service access, vibration exposure, and any local seismic or overhead-equipment requirements.
The review should cover the fixture weight and accessories, not just the luminaire body. Where a secondary safety cable is required, it should connect to a suitable structural point and be installed as specified. A safety cable is not a substitute for a primary mounting system, and a convenient nearby pipe or cable tray should not automatically be treated as an approved support.
Check Clearances and Service Access
Before drilling, fastening, or lifting, confirm clearances around the fixture, driver, emergency battery, sensor, junction box, and adjacent services. The installation must leave enough access for inspection, cleaning, driver replacement, battery testing, and safe future work. A fixture can be mechanically secure but still be poorly installed if its driver or emergency test point cannot be reached.
Check for conflicts with sprinkler coverage, cranes, conveyors, ducts, roof members, doors, storage racks, and maintenance platforms. In industrial spaces, the final position should preserve the intended light distribution without creating an obstruction or a service hazard.
Use an Installation Hold Point
A practical project control is a hold point before the first production installation. At this point, verify one representative mounting assembly against the approved drawing and the model instructions. Confirm the support, hardware, secondary retention, cable path, clearances, and fixture orientation. Photograph the accepted arrangement and use it as the installation reference only where the remaining locations have the same conditions.
Do not copy the first installation to different structural conditions without checking them. A surface-mounted bay, a suspended roof truss, and a cable-supported zone may require different approved accessories and different verification.
3. Choose and Install a Model-Supported Mounting Method
Compare Methods by Project Conditions
Pendant, chain, aircraft cable, surface, and bracket mounting are not interchangeable installation types. A method may be suitable only when the exact luminaire, accessory, support structure, and project documents approve it. The sequence below is a field-planning framework, not a substitute for the product installation manual. If the manual does not list the method or accessory, do not proceed on the assumption that the fixture can be adapted.
| Mounting method | Installation sequence | Result to verify before release |
| Pendant or stem | Confirm the approved fixture interface and drop length; secure the pendant to the reviewed structural point; attach the fixture without side-loading the interface; set the planned elevation and check sway | Interface, structural connection, plumb drop, final elevation, clearance and secondary retention match the approved documents |
| Chain suspension | Confirm the approved chain/accessory kit; attach the upper end to the structural point and the lower end to the fixture’s approved suspension point; adjust both sides evenly; install secondary retention where specified | Chain and attachment points are approved, the fixture is level, the load path is structural, and the final height is recorded |
| Aircraft cable | Use the listed cable kit and termination method; connect the upper termination to the reviewed support; connect the lower termination to the fixture points; tension and adjust each suspension point evenly | Terminations are locked, cable paths are not damaged or kinked, the fixture is level, and anti-sway or safety provisions are complete |
| Surface mount | Confirm the model-specific bracket and substrate; position and mark the approved holes; install the bracket using the project-approved fastener system; attach and orient the fixture; verify heat and service clearances | Bracket, substrate, fasteners, orientation, clearance and service access are accepted by the relevant reviewer |
| Adjustable bracket | Confirm the permitted bracket range and aiming direction; attach the bracket to the reviewed support and fixture interface; set the design angle; secure the adjustment; check the actual beam direction against the layout | Angle, locking arrangement, support, vibration condition and optical aim match the approved layout |
For every method, use the same control sequence: **identify the approved accessory → verify the structural point → attach the primary mounting → install secondary retention if specified → adjust height and level → protect the cable entry → photograph and record the result**. Do not invent universal wire colors, fastener sizes, torque values, or accessory ratings.
Installation Steps: Purpose, Action, and Verification
**Purpose:** create a repeatable installation rather than treating the fixture as a loose object to be hung.
- **Stage the approved components.** Match the fixture, mounting kit, secondary retention, cable-entry parts, control components, and emergency components to the luminaire schedule. Verify the result against the current model documentation.
- **Prepare the support.** Confirm the structural point, access platform, isolation boundary, and work area. The support must be accepted for the installation; a nearby pipe, cable tray, or non-structural service is not automatically a mounting point.
- **Attach the fixture using the listed interface.** Keep the fixture supported during attachment and prevent impact, twisting, or side-loading. Follow the exact manual for the connection order and fastener treatment.
- **Set height, level, and orientation.** Measure from the project’s defined reference, adjust suspension points or brackets, and align the fixture to the approved coordinate and row direction.
- **Complete secondary retention and cable protection.** Install the specified safety cable or secondary device, then route and seal the cable entry using approved components. Secondary retention does not replace the primary mount.
- **Perform the hold-point check.** Confirm identity, mounting method, support, level, height, orientation, clearances, enclosure condition, service access, and recorded photographs before repeating the arrangement at other locations.
FY High Bay Mounting Options: What Can Be Confirmed
The supplied FY product information confirms the current HB-E, HB-F, HBG, and HB-C product families and their application-related specifications, but it does not provide a complete public accessory matrix or installation manual for every model and configuration. Therefore, this article does not claim that any one of these series universally supports pendant, chain, cable, surface, or bracket mounting.
For a project-specific confirmation, request the current installation manual or approved submittal for the exact series, wattage, housing, accessory, and mounting condition. The confirmation should show the fixture interface, accessory part number, permitted orientation, structural connection, secondary-retention requirement, cable-entry arrangement, and any clearance or service limitation. This is the point at which a general installation method becomes an FY-specific installation instruction.
Preserve the Optical Intent
Mounting hardware changes more than mechanics. A different drop, tilt, row direction, or bracket angle changes where light reaches the work plane. If the approved layout assumes a horizontal fixture and the installer tilts it to clear a beam, the result may include dark zones, glare, excessive overlap, or light spilling outside the target area.
For a design change, record the reason and obtain a layout review rather than accepting the change because the fixture still illuminates. The practical question is whether the revised position still meets the project’s target and uniformity requirements under the actual mounting conditions.
4. Set Height, Position, and Orientation From the Approved Layout
Use Coordinates, Not Visual Spacing
“Hang the lights evenly” is not a commissioning method. Each fixture should have a location reference, mounting elevation, orientation, and optic or distribution type. The reference may be a grid intersection, a dimension from a column line, an aisle centerline, or another controlled coordinate system.
Mounting height is normally measured from a defined reference, such as the finished floor or the work plane, to a defined point on the luminaire. Confirm that everyone uses the same reference. A drawing that states 8 m above finished floor is not equivalent to 8 m above a raised work platform if the work plane is different.
Why Height and Orientation Affect Performance
Increasing the distance between the luminaire and the work plane generally spreads light over a larger area, but it also changes illuminance, spacing requirements, glare exposure, and the number of fixtures required. Optics and ceiling reflectance further change the distribution. A higher installation is not automatically better, and a higher-lumen fixture is not automatically a substitute for a correct layout.
Rows should be aligned with the actual aisle, production line, rack face, or work area identified in the design. In a warehouse, an optic aimed across the aisle instead of along it can alter vertical visibility and create uneven illumination on rack faces. In a manufacturing area, equipment height and shadowing may be more important than the nominal floor area.
Practical Initial Planning for Height and Spacing
For an initial layout, collect four measurements before selecting a final mounting position: finished-floor elevation, work-plane elevation, available structural elevation, and the dimensions and orientation of the target area. Then compare the proposed fixture spacing with the selected optic and the layout’s predicted illuminance and uniformity. A narrow distribution may require closer row spacing or more careful alignment; a wider distribution may cover a larger area but can increase spill light or glare if the layout is not reviewed.
Use the following sequence for a preliminary plan:
- Define the work plane, such as a production surface, aisle floor, or rack-face measurement plane.
- Measure the proposed luminaire elevation from the same reference used in the drawing.
- Place fixture coordinates over the actual columns, aisles, equipment, obstructions, and maintenance paths.
- Compare spacing and orientation with the selected model’s photometric file and the project target.
- Rerun DIALux or another approved photometric simulation when the model, optic, mounting height, spacing, orientation, work plane, or major obstruction changes materially.
This process gives the installer useful initial guidance without creating a wattage-to-height table that could be misapplied to another product or facility. Detailed fixture quantity and spacing calculations should be handled in the project’s dedicated lighting-design or calculation guide and then confirmed against actual field conditions.
Illustrative Coordinate and Height Verification
Consider a hypothetical installation with a finished-floor reference of 0 m. The approved drawing places a fixture at grid coordinate A-4, with the luminaire mounting point at 8.0 m above finished floor and the work plane at 0.8 m. The vertical distance from the luminaire to the work plane is therefore:
`8.0 m − 0.8 m = 7.2 m`
During the hold-point inspection, the installer records the actual mounting point at 7.85 m above finished floor and finds that the fixture is shifted 0.35 m toward the adjacent aisle. The deviation is not automatically acceptable or unacceptable from this calculation alone. The project team must compare it with the approved layout tolerance and, if necessary, rerun the photometric check using the actual coordinate and height.
This is a positioning verification example, not an electrical design calculation and not a universal tolerance. The approved layout, model photometric file, mounting height, work plane, ceiling conditions, and local acceptance criteria determine the decision.
Record Changes Before Concealing Them
If a beam, duct, sprinkler, or access condition forces a change, record the original coordinate, actual coordinate, original height, actual height, orientation, mounting method, and reason. A marked-up drawing is more useful than a verbal instruction because it lets the commissioning team connect measured light levels to actual fixture positions.
5. Protect Cable Entries and Enclosure Integrity
Treat the Entry as Part of the Luminaire System
A high ingress-protection rating applies to a defined product configuration and test condition. It does not automatically transfer to an incorrectly sized gland, an unsealed junction box, an open unused entry, a damaged cable, or a poorly routed conductor. Cable entries should therefore be reviewed as a complete system: entry device, seal, cable, bend radius, junction point, drain or drip path, and enclosure interface.
For wet, dusty, washdown, or food-processing areas, route cables so water cannot run along the cable into the enclosure. Avoid unsupported weight on the entry, sharp bends, abrasion, and low points that collect liquid. Fit unused openings with the approved closure method. Do not drill extra holes in a housing unless the manufacturer and project documentation explicitly allow it.
Apply the Product-Specific Environmental Boundary
FY LIGHTING’s current product information shows different protection levels across high-bay families. HB-E and HB-F are listed with IP44, while HBG is listed with IP65. HB-C is listed with IP69K and is positioned for food-area linear high-bay applications; NSF and other certification claims must remain tied to the specific covered configuration and documentation. These values should not be generalized across all FY or all industrial fixtures.
The installation environment still matters. IP65 or IP69K does not by itself prove suitability for every chemical, cleaning agent, food-zone location, temperature, impact condition, or electrical configuration. Confirm the complete project requirement, including the junction box, connectors, cable glands, and adjacent equipment.
Keep Enclosures Serviceable
Do not place a junction box or driver where it will be buried above insulation, blocked by a duct, or exposed to a cleaning method outside its rating. Label circuits, control zones, emergency units, and isolation points in a way that remains readable after handover. If the fixture has a removable driver or serviceable component, leave the access required by the product documentation.
6. Coordinate Emergency and Sensor Components
Define the Intended Sequence Before Installation
Sensors and emergency options should be designed as operating sequences, not added as isolated accessories. Document the normal occupied state, unoccupied state, daylight response, manual override, timeout or delay, emergency behavior, and failure state. Identify which zones are linked and which fixtures respond independently.
A sensor’s field of view, mounting position, height, obstructions, and commissioning settings can change the result. A sensor mounted behind a beam may miss occupants; one aimed toward a bright loading door may respond differently from one inside a rack aisle. Confirm the coverage and adjustment method with the exact sensor documentation.
Match Interfaces and Configuration
Verify the driver, sensor, dimming method, control voltage, protocol, emergency battery, test facility, and configuration-specific options. Do not assume that a sensor or wireless control option on one product family is available on another. Match the control interface to the exact driver and approved control diagram, and record the final settings for commissioning.
The HBG product information identifies optional smart sensors and up to 90-minute emergency backup. That option must be confirmed for the selected HBG configuration and project requirements; it should not be generalized to every high-bay family.
Test More Than “It Turns On”
Commissioning should test normal operation, vacancy response, daylight interaction, manual override, emergency transfer, return to normal, and the defined failure state. Record the settings and test conditions. If the installation is completed during daylight, repeat the relevant sensor test under representative conditions or document the limitation and schedule a follow-up.
7. Commissioning and Handover
Use Five Check Categories
Commissioning should cover mechanical, electrical, control, emergency, and lighting outcomes. The sequence below is a management framework; qualified personnel must perform the actual electrical and safety work according to the approved documents.
- **Mechanical:** Confirm fixture identity, mounting method, support, secondary retention, orientation, clearances, enclosure condition, and service access.
- **Electrical:** Confirm isolation and inspection steps, supply identification, protective devices, cable entries, grounding or bonding requirements, labels, and approved connections.
- **Controls:** Confirm zone assignment, sensor coverage, dimming response, schedules, overrides, default state, and loss-of-control behavior.
- **Emergency:** Confirm test access, transfer behavior, duration requirement, indicator status, return to normal, and records for battery or emergency components.
- **Lighting:** Measure or verify the required points from the approved layout, including work-plane height and representative operating state. Investigate unexpected dark areas, glare, excessive variation, or changes caused by construction obstructions.
Commissioning Record Fields
| Record field | Example evidence to retain |
| Fixture identity | Series, wattage, serial or batch reference, location and accessory code |
| Mechanical acceptance | Mounting method, support check, secondary retention, orientation and photographs |
| Electrical acceptance | Qualified inspection record, circuit or zone reference, supply confirmation and labels |
| Control settings | Zone, sensor mode, delay, daylight response, override and default state |
| Emergency test | Test date, transfer result, duration requirement, indicator and corrective action |
| Light verification | Measurement plan, meter or simulation reference, work-plane height, readings and deviations |
| As-built change | Original location, actual location, actual height, reason and approval |
| Handover | Manuals, approved drawings, settings, spare parts, warranty documents and open issues |
A commissioning record should make it possible for another qualified person to understand what was installed, how it was configured, what was measured, and what remains unresolved. Use the same record as the handover package rather than creating a second checklist that repeats the installation sequence.
The completed handover record should include:
- Approved and as-built fixture layout, including actual height, coordinates, orientation and any approved deviations.
- Exact series, wattage, accessories, controls and emergency configuration.
- Mounting method, support verification, secondary-retention record and representative photographs.
- Circuit, zone, sensor, override, control and emergency test settings.
- Light-level or photometric verification records, including work-plane height and measurement conditions.
- Product manuals, maintenance instructions, spare-part information and warranty documentation.
- Open-item list with owner, due date, corrective action and acceptance status.
For FY LIGHTING products, warranty terms should be checked against the final model, configuration, sales documents and intended operating environment. Do not rely on a generic family statement when the project requires a contractual warranty decision.
8. FY LIGHTING Installation and Custom Mounting Support
The right FY LIGHTING fixture depends on the application and the installation conditions, not only on nominal wattage. The current range includes HB-E and HB-F linear high-bay families, HBG tri-proof high bay lighting, and HB-C food-area linear high-bay lighting. Their published configurations and protection levels differ, so the product selection should follow the facility conditions, mounting method, optical layout, voltage, controls, and required documentation.
FY LIGHTING can support project-specific lighting review, CAD or DIALux coordination, layout development, sample evaluation, and online engineering guidance. The useful starting information includes the building plan, mounting structure, mounting height, fixture quantity, work-plane height, target lighting level, aisle or process orientation, input voltage, control requirements, environmental exposure, required certifications, and local installation constraints.
This support does not transfer installation responsibility. The local contractor, qualified electrician, structural reviewer, and project authority must approve and execute the work within the applicable requirements. Where a custom bracket, mounting arrangement, or project-specific configuration is needed, it should be reviewed before quotation and documented in the approved submittal.
Conclusion: Install From Verified Conditions, Not Generic Rules
The safest way to install and hang LED high bay lights is to control the sequence: approve the exact product and layout, verify the structure, select a documented mounting method, set each fixture from coordinates and height references, protect every cable entry, configure controls and emergency components, and commission the complete system. Universal height, hardware, wire, torque, or certification rules are not reliable substitutes for model documents and local qualified work.
Planning a commercial high-bay installation? Share the mounting structure, installation height, fixture quantity, voltage, control and emergency requirements, environmental conditions, target layout, and local requirements with FY LIGHTING. The team can help review a project-specific product family, mounting approach, and lighting layout before accessories and final configuration are confirmed.
FAQ
Can I install LED high bay lights without a qualified electrician?
Mechanical placement and access planning still require trained personnel, but electrical isolation, connections, inspection, and energization must follow local requirements and be performed by qualified personnel where required. This guide does not replace the installation manual, lockout/tagout procedure, structural review, or electrical inspection.
How high should LED high bay lights be mounted?
There is no universal height that fits every facility. The correct height depends on the approved photometric layout, fixture optic, target work plane, ceiling conditions, mounting structure, glare requirements, and required uniformity. Verify the actual elevation against the layout rather than choosing a height from wattage alone.
Which high-bay mounting method is best?
The best method is the model-supported method that satisfies the structure, service access, environment, optical orientation, vibration, and local requirements. Pendant, chain, cable, surface, and bracket methods each require different verification. The selected accessory and installation manual should control the final decision.
Does IP65 or IP69K make every installation waterproof?
No. The rating applies to the tested product configuration and conditions. Cable glands, unused entries, junction boxes, connectors, seals, installation orientation, and adjacent equipment can still create a weak point. Confirm the complete installed system and the actual cleaning or environmental exposure.
Can I add sensors or emergency backup after installation?
Only if the exact luminaire and project configuration support the option. Sensor coverage, driver interface, emergency battery, test access, control wiring, and enclosure integrity must be checked before installation. For example, HBG documentation identifies optional smart sensors and up to 90-minute emergency backup, but that does not automatically apply to every series.
What should be measured during commissioning?
Record the actual fixture identity, mounting position and height, mechanical condition, control settings, emergency behavior, and light-level verification under defined conditions. The measurement plan should identify the work plane, points, operating state, instrument or simulation reference, deviations, and corrective actions.
How Do You Hang High Bay Lights From a Metal Building?
Start by identifying the actual structural member and obtaining approval for the proposed connection. Then use only the luminaire’s listed suspension accessory and connect it to the reviewed support point. Do not attach a fixture to metal roof panels, purlins, cable tray, pipe, or another building element simply because it is nearby. Verify the load path, secondary retention, height, level, cable entry, and service clearance before repeating the installation.
Can LED High Bays Be Surface-Mounted?
Some high bays can be surface-mounted, but this is a model- and accessory-specific question rather than a category-wide feature. Confirm the exact bracket or hole pattern, substrate capacity, heat clearance, orientation, service access, and photometric effect in the current installation documents. If the selected model does not list surface mounting, use a different approved configuration rather than modifying the housing.
What Is the Difference Between Hook and Suspension Mounting?
Hook mounting usually uses a defined hook or eye interface, while suspension mounting may use a pendant, chain, or cable assembly between the structural point and the luminaire. The practical difference is the approved fixture interface, load path, adjustability, sway control, and accessory documentation. Use the terminology shown in the exact product manual; do not substitute a visually similar hook or suspension part.
How Do You Keep Suspended High Bays Level?
Use the approved suspension points and adjust them evenly while measuring the fixture against a defined horizontal reference. Check the level after cable routing and secondary retention are complete, because cable tension or an uneven support point can change the position. Record the final orientation and compare it with the lighting layout. The allowable adjustment range and accessory method must come from the model documentation.
Can Existing High-Bay Mounting Points Be Reused?
Existing points can be reused only after their condition, capacity, location, fastener system, corrosion, vibration exposure, and compatibility with the new fixture and accessory have been reviewed. The old point may not match the new load path or coordinate. Treat reuse as a project approval decision, not as proof that the point is suitable because another fixture was previously installed there.
Sources
- OSHA Lockout/Tagout: Control of Hazardous Energy
- OSHA Electrical Safety
- FY LIGHTING linear high-bay lighting collection
- FY LIGHTING HB-E linear high-bay light
- FY LIGHTING HB-F linear high-bay light
- FY LIGHTING HBG tri-proof high-bay light
- FY LIGHTING NSF food-area linear high-bay light
- FY LIGHTING industrial LED lighting